A / The Project
A 1,400-square-metre rug, laid in three quadrants, that never once closed the front door.

N° 071 · Commercial

01Overview

A mid-rise office tenant wanted their entrance to feel like an address, not a parking lot. We replaced asphalt, planters, and a fragmented walkway with a single 1,400 m² plaza in two-tone granite, set in a precise running-bond pattern that reads as a single rug from the lobby's mezzanine.

02The Challenge

The plaza had to remain operational throughout — emergency-vehicle access could not be lost for more than six hours, and the underground parking ramp directly beneath limited bearing capacity to a strict slab loading.

03The Approach

We staged the work in three quadrants, kept a continuous fire-route open at every phase, and specified a 60 mm granite paver over a polymer-modified bedding mortar bonded to the existing concrete deck — the system carries the live load without adding mass.

B / Transformation

From what was there to what should have been.

Box Grove Plaza (after)
Box Grove Plaza (before)
BeforeAfter
Before2023 · spring
After2023 · completion
C / Materials

Materials used

  • M.01Cambrian black granite — 60 mm sawn finish
  • M.02Cambrian grey granite — 60 mm sawn finish
  • M.03Polymer-modified bonded mortar bed
  • M.04Permeable polymeric joint sand
  • M.05Stainless restraint at every column
D / Scope of Work

What we delivered

  1. 01Phased demolition (3 quadrants)
  2. 02Continuous fire-route maintenance
  3. 03Bonded mortar-bed installation
  4. 04Running-bond paver layout
  5. 05Drainage & expansion joint design
  6. 06Night-shift lighting commissioning
E / Gallery
01Twilight at the main entrance.
02Running-bond field meets the building grid.
03Threshold detail at the revolving doors.
04Two-tone joint — Cambrian black + grey.
05Setting-out drawings on site.
06Evening lighting commissioning.
F / On Site

The craft, day by day.

Wk 01 — First quadrant — asphalt lifted.
Wk 01
First quadrant — asphalt lifted.
Wk 02 — Bonded mortar bed at slab interface.
Wk 02
Bonded mortar bed at slab interface.
Wk 03 — Running-bond set against datum line.
Wk 03
Running-bond set against datum line.
Wk 04 — Custom cuts at the tower columns.
Wk 04
Custom cuts at the tower columns.
Wk 05 — Permeable joint sand application.
Wk 05
Permeable joint sand application.
Wk 06 — Final clean ahead of public open.
Wk 06
Final clean ahead of public open.
— Studio

Every Anissa Inc. project begins the same way: a quiet walk of the property, a measuring tape, a sketch.